Generator Care Info

Rated Generators are designed to run with 10 load forGas engine Gas lines and connections, carburettor and
the duration of an outage with no overload availablelinkage, magneto/distributor, ignition system, spark plugs
" Load MUST be reasonably balanced/distributed1. Insulation test Main stator, main rotor, exciter stator,
across all the three phasesexciter rotor
" The AMF panel is used correctly in accordance with1.Load testing
manufacturers instructions Maintenance must beWith full load, perform a two to four hour load test
carried every 6 months by a qualified generatorOverall Energy Systems Testing
engineerAs well as performing the periodic Planned
" A test certificate is issued each service/maintenanceMaintenance of each part of the system, consideration
visit every 6 months Only approved parts are usedshould be given to testing the entire system on a
" All work and maintenance records are kept availableregular basis.
" Any irregularities visual or otherwise are reported inAn overall system test will involve putting the critical
writing immediatelyload at risk so careful arrangements and agreements
" All fuel,oil,water and other fluid levels to be kept fullmust be made.
" Generator is never allowed to run out of fuel or oilMains Failure Test
etc whilst holding the loadDisconnect the mains supply to the protected power
" Generator is never over-loaded and never allow theequipment for an extended period and check:
Generators to run lightly loaded for long periodsWith no generator :
" Generator is run off load once every week for a" the UPS battery supports the critical load for the
test of 5 minutes maximumexpected autonomy time
" Generator is run with load once a month" all alarms and control signals are correct
" Generator enclosure is checked for any possible" the critical load responds correctly to any signals
tempering ( i.e. has the emergency stop button beenreceived from the UPS equipment e.g. system alarms,
pressed and not reset?)orderly shutdown sequence etc.
" Someone is appointed as the responsible person toIf a generator is installed:
overlook implementation1. the Automatic Mains Fail (AMF) equipment operates
Generator Maintenance and Testingcorrectly
A regular generator service program should include2. the generator auto-starts after the expected time
tests and checks of the following:3. the generator output supply is correct and within
1. Cooling systemacceptable UPS input limits.
Radiator/heat exchanger, coolant, hoses and4. the UPS accepts the generator supply
connections, fan drive pulley and fan, fan belts, jacket5. battery recharging takes place while the UPS is
water heater, water pump, thermostats.being supplied by the generator.
1. Fuel systemMains Restoration Test
Fuel tank, water trap/separator, fuel lines andFollowing the Mains Failure Test, re-connect the mains
connections, governor and controls, fuel filters - primarysupply to the protected power equipment and check:
secondary, fuel pressure, air induction and exhaustWith no generator:
system, air filter, air filter service indicator, air inletIf the UPS is fitted with auto-restart facilities,
system, turbocharger, exhaust manifold, valves and1. The system returns to normal operation
valve rotators.automatically, otherwise all UPS modules can be
1. Lubrication oil systemre-started manually and the system restored to normal
Oil, oil filters, oil pressure, crankcase breatheroperation
1.Starting system2. All alarms can be reset.
Batteries, battery specific gravity, battery charger,If a generator is installed :
starting motor, alternator, engine monitor and safety" the Automatic Mains Fail (AMF equipment operates
controls, gauges, remote annunciators/alarmscorrectly
1.Generator" the UPS signals a mains failure during the
Bearings, slip rings and brushes, space heaters,changeover
vibration isolators" the generator shuts down after the expected time
1.Control panel" the UPS accepts the restored mains power supply
Start controls ? manual/auto, voltmeter, ammeter,and recharges the batteries
frequency meter, circuit breaker, auto transfer switch 1." all alarms can be reset.